NLRSD provides school construction update

Custom Search 2

The North Little Rock School District recently provided the general public an update on how the construction was progressing at several city elementary schools.

“The following items are completed or in process,” reads a recently published report.

Meadow Park Elementary

Pre-Construction Site Package

Bethany RCP and inlet structures are 95 percent complete or near completion; Eureka Garden RCP installation of storm drainage will be complete soon; RCP on Eureka Garden across the existing school driveway will take over the next couple weekends. One drive has been installed.

Building Package

Footings are complete. Last section poured on Oct. 23; Under slab plumbing is complete; Section “A” of building slab was poured Oct. 11; Section “B” of building slab was poured Oct. 4; Section “C” of building slab was poured Oct. 31; Section “D” of building slab was poured Nov. 4; Temporary power has been run for construction; Main telephone conduit installed to main telephone rooms; Under slab electrical is complete; Steel delivered to site on Nov. 4; Steel erection started in section “B” on Nov. 4.

Lakewood Elementary

Pre-Construction Site Package

Phase 1 site work is completed; Removal of excess dirt from site.

Building Package

Foundations have begun; Section “D” footings are complete and building slab was poured Oct. 29; Section “A” footings are complete; Section “C” footings will begin this week; Section “B” footings will begin this week; Section “A” building slab will be poured Nov. 5; Section “D” under slab plumbing is complete; Section “A” under slab plumbing is complete; Under slab plumbing is underway for sections “C” and “B.”

Under slab electrical is also underway and temporary power for site; Elevator pit has been dug; Letters for pour dates are being distributed to the surrounding neighbors; Next concrete pour will be section “C” and should happen during regular work hours due to size of pour; Steel will be delivered to site soon.

Amboy Elementary

Pre-Construction Site Package

Phase 1 Site Work is completed; Building grid lines have been laid out.

Building Package

Amboy has now been bid and Board approval has been given. Contractors are getting contracts for subs in place. Subcontractor mobilization should begin soon.

Boone Park Elementary

Pre-Construction Site Package

Site Utility is complete; Redstone remobilized two weeks ago and finished building pad 10/18/13; Site dress up; Grid lines for building will be laid out this week.

Building Package

Boone Park has now been bid and Board approval has been given. Contractors are getting contracts for subs in place.Subcontractor mobilization should begin soon.

High School

Pre-Construction Site Package

Phase 1 High School Site Package is 100 percent complete except for sewer line “B” that added new scope of work; Grade of building pads A & B is complete; Site dress up; Grouting of old sanitary line is complete; Construction parking across Main St. has been fenced for use; Sewer line “B” bore pit started Oct. 10; Boring will start Oct. 28; 40 feet out of 350 feet of boring has been made thus far.

Building Package

Athletic Facility was bid on Oct. 10.

SLC-1 Foundation Package was bid on Oct. 17.

— Greg Rayburn